![]() | Vol. 3 No. 3 Winter 1995 |
| A Newsletter About New Jersey's Water Quality Programs |
Note: Adopted rule changes allow the New Jersey Wastewater Treatment Trust to finance the local share of projects funded through the Pinelands Infrastructure Trust. Adopted rule changes are applicable to all projects not closed out.
If you have any questions regarding the impact of these amendments on your wastewater project, please contact Stanley Cach, Chief, Bureau of Engineering North at (609) 292- 6894 or George Goldy, Chief, Bureau of Engineering South at (609) 984-6840, as applicable. For general issues regarding the rule readoption with amendments, please contact Theresa Fenton, Chief, Bureau of Program Development and Technical Services, at (609) 292-3859.
| Category | Old Rules | New Rules |
|---|---|---|
| Administrative Expenses | Limited to 1% of Building Line Item | Limited to 3% of Building Line Item and now includes:
|
| Engineering Expenses | Limited to 12% of Building Line Item | No longer limited to 12% of Building Line Item, however, Professional Services Affidavit is required. |
| Building Expenses | Costs associated with house connections were unallowable | Costs associated with house connections will be allowable when owned, operated, and maintained by the Loan Recipient. |
| Contingency Line Item | Loan Contingency was unallowable | Contingency will be allowable limited to 5% of Building Line Item. |
| Planning and/or Design Allowance | P& D Allowance varied from 4.8% to 14.5% of Building Line Item. Design Allowance varied from 3.4 % to 8.6 % of Building Line Item. | P& D Allowance varies from 5.0% to 27.5% of Building Line Item. Design Allowance varies from 3.6% to 16.3% of Building Line Item. |
| Preaward Approval | Limited to top 100 projects on approved priority list. | All projects listed on the Priority List are eligible with prior DEP approval. |