 |
Site
Remediation News June
1999 (Vol 11 N0 1) Article
05
Protection Through Restoration
By: Rob Schrader
Bureau of Emergency Response
Division of Responsible Party Site Remediation
The Delaware Bay & River
The Delaware Bay and River receives 70% of all the crude
oil entering the ports on the eastern seaboard of the United
States.1 Approximately 1.25 billion barrels
of oil is imported on approximately 1,000 vessels that stop
at the Ports of Philadelphia and Wilmington.
The Delaware Bay and River is an important wetlands and
wildlife habitat. This sensitive area provides a safe harbor
for the nesting waterfowl, migrating waterfowl, non-game
species such as the Osprey (Pandion haliaetus) and
American Bald Eagle (Haliaeetus leucocephalus), and
wintering waterfowl. In addition to the waterfowl, the bay
supports a million or more shorebirds in late spring as
over 20 species migrate between Southern Hemisphere wintering
grounds and arctic breeding grounds. The abundant food resources
of the Delaware Bay, principally the eggs of the horseshoe
crab, allow shorebirds to store sufficient energy to complete
their migration. Because most of the world population of
certain species is concentrated along the shores of the
Delaware Bay at one time, oil spills have the potential
to cause catastrophic damage. Even spills that affect only
the food sources could result in a subsequent death of the
shorebirds requiring years for the populations to recover.
Along with the threat to shorebirds, other sensitive resources
are affected in and around this estuary, including shellfish,
sport, and commercial fisheries, diving waterfowl, and resident
birds. In addition, this area also provides a prime location
for recreation and eco-tourism for the public.
Protection Strategies
In the summer of 1990, the New Jersey Department of Environmental
Protection, Bureau of Emergency Response (BER) along with
the Delaware Bay River Cooperative (DBRC) surveyed approximately
75 miles of the New Jersey Shoreline from Cape May to the
Delaware Memorial Bridge. This survey was to plan strategic
protection strategies at each Gut, Creek, washout and tributary
that feeds the River. The final strategies were based on
the following hierarchy of controls: 1) physical processes
in the creek, gut or tributary; 2) protection priorities;
and 3) probable effectiveness of response.
Because the basic assumption was that the strategy be designed
to deal with spilled oil to the creeks from the open bay,
the protection strategies that were proposed emphasized
flood-tidal conditions. These proposed strategies were based
on the information at hand on wave action, tidal currents
and based on normal weather patterns for the area. The majority
of the areas have no vehicular access. The shoreline is
a high-energy shoreline that consists of root substrate,
mud and the indigenous grasses of the area. Of the 71 estuaries,
67 of them will need permanent anchor points because setting
traditional anchors would cause more environmental damage
and would in most cases not be strong enough to hold the
proposed boom. In addition, the permanent anchor points
would greatly reduce boom deployment time, thus averting
catastrophic damage to the wetlands making the pilings the
preferred method for the many areas. However, funding for
such pilings would have to be found. All these strategies
are now Annexed to the USCG Port of Philadelphia Area Contingency
Plan.2
The Spill
In October of 1996, while enroute to New York from Texas,
the barge Bouchard B155 carrying 150,000 barrels of #6 fuel
oil entered the Delaware Bay to weather out a Nor’easter
that was affecting the regional area. The B155 anchored
in the Bombay Hook anchorage 8.5 nautical miles from Nantuxent
Cove. The crew of the barge had been aware of oil in the
anchor compartment before anchoring.
On October 24, 1996, the NJDEP Bureau of Emergency Response
was notified that oil had been discovered on the shoreline
at the small coastal village of Point Bay, Cumberland County.3
The responsible party (RP) had accepted responsibility and
hired a clean up crew. The oil had formed “tar balls” and
fouled the entire length of the village. These tar balls
were mixed in with the rack line and consisted of vegetative
debris. The rack line was 4-5 meters wide and the coverage
of oil was patchy 20-30% to sporadic 5-10%.4
Studying the trajectory of the oil movement, it was probable
that oil had also affected an area just north of Point Bay.

Figure 1 |
| |
A survey of the 3.5 nautical mile area from Nantuxent Creek
to Ben Davis Point revealed that the oil had sporadically
affected the entire length of shoreline from waters edge
to approximately 30 meters into the marsh. Oil coverage
was patchy, with approximately 10% of the marsh area affected.
Within these patches, oil covered the upper half of the
marsh vegetation. A visible sheen was observed emitting
from the oil globules on the substrate and running into
the water (see Figure 1).
A decision not to clean the wetlands and not cut the grass
was based in part due to findings of a NOAA study on a spill
on the upper Delaware River, July 1992. In that finding,
NOAA scientist Edward Livine found that vegetation that
is light to moderately fouled with or with out cutting resulted
in no long-term negative impact. Flowering and seed production
by most of the vegetation in the affected areas had also
indicated that plants were not stressed by the oil or by
cutting any of the methods.5
Natural Resource Damage Assessment
According to 43 CFR 11.14, in most spills, a State trustee
shall act on behalf of the public as trustee for natural
resources, including their supporting ecosystems, within
the boundary of a state or belonging to, managed by, controlled
by, or appertaining to such state.6
In the event of an oil spill, in the State of New Jersey,
the state trustee, in conjunction with the federal government
trustees, work with the parties responsible for the spill
to restore any resulting injury to the public’s resources.
In most cases, before restoration* can
occur, the governments must first assess the type and extent
of the natural resources injury. Depending upon the specifics
of the spill, (oil type, weather, affected resources, etc.)
and the level of cooperation from the responsible party,
the assessment process and succeeding natural resources
restoration may take a considerable amount of time and money.
In order to speed the restoration of the public’s natural
resources and keep assessment cost at a minimum, New Jersey’s
Office of Natural Resource Damage (ONRD) has adopted a policy
of forgoing the assessment phase of natural resource restoration
in the event of very small spills with limited or ephemeral
natural resource injury. The decision to immediately pursue
restoration without assessment is made only after the responsible
party has agreed to a specific restoration project and the
cost of assessing injury will likely be greater that the
cost of the injury itself (or restoration thereof).7
The oil from the October 1996 barge spill that came ashore
in the Nantuxent Cove area of New Jersey was of relatively
low toxicity and limited extent, and deposited on vegetation
that had already begun its seasonal senescence. Therefore,
ONRD, NOAA, and the responsible party agreed that the spill
resulted in minor injury to the salt marsh and that a small
restoration project in the area of the spill would be an
appropriate measure to compensate the public for the injury.
Several restoration options were considered, but based
on a suggestion by the author, ONRD and NOAA determined
that construction of permanent boom anchors at the mouth
of the three creeks emptying into Nantuxent Cove was the
best option. The presence of the boom anchors would allow
for rapid deployment of protective booms in the event of
future oil spills, a level of protection that does not currently
exist in these ecologically sensitive areas.

Figure 2. |
| |
Representatives from NJDEP’s Office of Natural Resource Damage,
and Bureau of Emergency Response along with the DBRC visited
the area. Six poles were to be set. Two poles at each of the
creeks, one on the north side, one on the south. The creeks
were Back Creek, Cedar Creek, and Nantuxent Creek (see Figure
2).
The project was to be enhanced by the placement of osprey
(a threatened species) nest platforms in five of the six
boom anchor pilings. These pilings would have to be placed
at the mean high water mark and would have to be a single
pole structure with a platform on the top 14-16’ high. The
nesting box would include a perch equal or greater in height
to the nest on either side.
The Project
Because this was a new concept in protecting the wetlands,
the NJDEP’s ONRD drafted a Memorandum of Understanding (MOU)
where ONRD oversees the settlement and makes monies available
to BER for projects such as the installation of the booming
anchor poles.
The project needed both state and Army Corps of Engineers
permits for the installation. The permitting process was
both tedious and frustrating. Three of the six poles were
to be located on State Property; three were to be located
on private property. Permission was needed from the property
owners as well as from the three municipalities Planning
Boards and the Cumberland County Freeholders. All were highly
enthusiastic for the project.
The US Army Corps of Engineers was asked to participate.
They had a shallow draft construction barge with a 130’
crane, which was perfect for the Project. The US Army Corps
of Engineers entered a MOU with the NJDEP to install the
pilings. Public Service Electric & Gas, a utility in the
State and operators of the Salem Nuclear Power Plant, were
asked if they would donate six 35’ poles for the project.
Public Service Electric & Gas, Environmental Director had
no hesitations, six poles were slated for the project and
were delivered to the Fort Mifflin Army Corps of Engineers
yard in Philadelphia. The nests were built by Citizens United,
a non-profit organization that routinely builds, installs
and tends osprey nests on the Maurice River. The Cumberland
County Road Department under the direction of the Office
of Emergency Management delivered these nests.
Installation
The week of September 22, 1998 was selected for installation.
This week was selected because tides were favorable; having
a high tide in mid afternoon. The Barge Titan began the
installation process. With small river tugs, the barge and
crane were pushed to the pre-designated position on the
north side of the Nantuxent Creek. There they dropped the
barge stabilizers and set the pilings. Once the pole was
driven to a depth of approximately 20 feet, the nesting
box was installed on the top. Approximately 1.5 metes from
the bottom, a 12-inch eyebolt was through bolted for the
boom anchor. That afternoon the southern pole was set and
the nest was placed. The project was completed in four days,
one day over budget due to small logistical problems. In
all the installation of the Osprey nests/anchor points went
very well.
The Test
Since the original survey in 1990, DBRC has been testing
and proving all of the strategies for the Delaware River.
In only two incidents, was DBRC activated to boom off any
NJ creeks in the lower Delaware Bay.
In response to the NJDEP installing the anchoring points,
DBRC pledged that they would test the pilings in Back Creek,
the northern most creeks in Nantuxent Cove.
On October 19, 1998, DBRC arrived at Cedar Creek at 8 am
with a small barge loaded with 3,000 feet of boom, 3 small
boats and 10 men. Tides that day were favorable, low tide
being at 0810 and high tide at 1315. Currents were averaging
1.2 knots.

Figure 3 |
| |
The boats were launched and working with the flood tide, they
had placed the 3,000 feet of boom with 20 anchors across the
mouth of Back Creek within 3 hours. According to the contractor
S&D Environmental Services Field supervisor, the placement
of the boom was made easier by the poles. The poles not only
gave them a landmark, but they were able to connect the boom
immediately without destroying the marsh substrate by digging
in anchors (see Figure 3).
Conclusion
This unique pilot project will drastically shorten the
response time to place protective booms in remote locations.
In most cases, an oil spill in the Delaware Bay does not
go unnoticed. Lead-time and trajectories for where the oil
will impact are made by NOAA to the Coast Guard. The RP
will direct DBRC or a contractor to boom the area. Although,
boom placement has been pre-designated in the Area Contingency
Plan, the contractor if not familiar with the area can only
guess where the boom is to be placed to be effective. In
most cases, the response time to the area would be 2-3 hours
and then possibly 5 hours to boom any one of the creeks.
With the nesting poles/booming anchors in place, the 6-8
hour response time to these remote areas will be cut in
half. With the pre-designated anchor points, there is no
question where the boom will be placed and with the rapid
response, damage to the wetlands is reduced; thus, damage
assessment and clean up costs are reduced. The booming anchor/osprey
habitat concept is good for both the environment and for
the shipping industry.
The Bureau of Emergency Response has been a working partner
with DFG&W/ONRD on numerous spills since the October 1996
incident on the Delaware River. This partnership has provided
the State of New Jersey numerous projects on many of our
creeks and rivers. At this time, settlements from spills
in the Pennsauken Creek and the Woodbridge Creek have provided
monies for the protection of these valuable estuaries as
projects pending. The New Jersey Department of Environmental
Protection has taken a step in the protection of the Delaware
Estuary and to the wetlands along our shoreline.
The concept of Protection through Restoration is new. The
success of this pilot program and the overall acceptance
by industry, ONRD, NOAA, DFG&W, and The U.S. Department
of Interior, has enabled this concept to blossom to national
notoriety and will continue to provide protection to our
riverine and coastal environment for years to come setting
nesting poles/booming anchors where needed.
-
R.Glenn Ford, Ecological Consulting,
Inc November 1992
-
USCG Port of Philadelphia Area Contingency
Plan, Sensitive Area Annex
-
NJDEP UCN 96-10-24-1806, Tank barge
B155, Bouchard Transportation, R. Schrader, OSC
-
Shoreline Oiling Assessment Field
Book, No.X-255
-
“Follow Up Study on Oiled Vegetation
Cutting Along The Delaware River, Edward Levin, SSC
NOAA, 1995
-
43 CFR 11.14(I) Damages set forth under
section 107(a) CERCLA
- Text provided by John Sacco, NJDEP,
Division of Fish Game & Wildlife, Office of Natural Resource
Damage, 1998
* Restoration or rehabilitation- means
actions undertaken to return an injured resource to its
baseline condition, as measured in terms of the injured
resource’s physical, chemical, or biological properties
or the services it previously provided, when such actions
are in addition to response actions completed or anticipated,
and when such actions exceed the level of response actions
determined appropriate to the site pursuant to the National
Contingency Plan .
|
 |