Appendix III

Alternative Ground Water Sampling Techniques Guide (July 1994)

ALTERNATIVE GROUND WATER SAMPLING TECHNIQUES
MATRIX SUMMARY

Tool Construction Floating Product Thickness Detection Groundwater Flow Determination Depth Limits Sample Confined Aquifer Vertical Profiling Installation Dutration Placement Method Purge Required Sampling Method
Screened Auger CS Yes Estimate 150' Yes (a) Yes less than 48 hrs DR Yes B,I,P,E
Miniature Drive Point SS, PTFE No No 40' No No less than 48 hrs E/Hy, H No P,E
Well Point SS, CS Yes Yes(b) 150' Yes (a) Yes less than 48 hrs(c) DR, E/HY, H Yes B,I,P,E
Passively Placed Narrow Diameter Points SS, PVC Yes Estimate 10' No No less than 48 hrs E/HY, H Yes B,I,P,E
Small Diameter Direct Push Points SS, PVC Yes
(Slotted points only)
Estimate 80' No Yes(d) less than 48 hrs E/HY Yes
(Slotted points only)
B,I,P,E
Hydropunch Direct Push Sampler SS, PVC Yes
(HP-II only)
Estimate 250' Yes(a) Yes less than 48 hrs DR No B,I,P,E

 

(a) Provided intermediate casing is used to isolate unconfined aquifer.

(b) If permanent installation. If not, then only an estimate.

(c) Longer installations are permitted however, installation must follow monitor well installation specifications and permit requirements.

(d) Only using blank casing with sealed point.

 

 

CS - Carbon Steel
SS - Stainless Steel
DR - Drill Rig
E/HY - Electric or Hydraulic
H - Hand
B - Bailer
I - Inertial Pump
P - Peristaltic Pump
E - Evacuation Chamber