Governor Phil Murphy • Lt. Governor Tahesha Way
  Search
new jersey department of environmental protection
NJ Home Page Services A to Z NJ FAQs NJ Departments/Agencies departments
site remediation program

SRP Home | DEP Home

Crumb1 Crumb2 Current

 

SRP Publications Annual Reports 1998

III. Progress at Contaminated Sites (cont.)

98 SRP ANNUAL REPORT

Remedial activities conducted under state authority

Cleanup activities at Non-NPL complex sites

Complex sites are defined as sites or subsites that require a full scale study, formal design and response to an unknown and/or uncontrolled source or release. These actions can be funded by responsible parties or with public monies. Progress at publicly funded subsites during SFY98 included the start of the following projects: 25 Remedial Investigation and Remedial Alternatives Analyses (RI/RAA); one Remedial Design (RD); nine Remedial Actions (RA); and two Operation and Maintenance actions. Furthermore, seven publicly funded Remedial Action projects were completed in SFY98, along with four Remedial Investigation/Remedial Alternatives Analyses and three Remedial Design projects.

In terms of privately funded actions in SFY98, 41 Remedial Action Workplans were approved, which mark the beginning of actual cleanup work at these responsible party sites. Also, 52 privately funded Remedial Action Reports, which represent the completion of responsible party cleanups, were approved during SFY98.

As of June 30, 1998, 150 publicly funded projects were underway, some of which began in previous years. In addition, 220 privately funded non-NPL complex projects also were underway at that time.

 

Non-NPL SFY98
Cleanup Activities

Funding SourceStartedCompleted

Public Funds

9

7
Private Funds4152
Totals5059

 

Focused Cleanup Activities

A focused cleanup is defined as a remedial measure, usually with no formal design phase, that consists of a focused response to a known source or release. The Site Remediation Program's Bureau of Field Operations, located in two regional field offices, oversees a large number of focused cleanups ensuring compliance with environmental laws and regulations. In SFY98, some 1,721 of these cleanups were guided to completion. There were 2,612 cleanups underway at the end of SFY98. A consistent increase in cleanups underway has occurred each year for the past three years.

 

Focused Cleanup Activities

TypeSFY96SFY97SFY98

Cleanups Underway1,9232,0512,612
Cleanups Completed1,1321,7211,721

 

Industrial Site Recovery Act Cases

The Site Remediation Program's ISRA group oversaw completion of 59 cleanups during SFY98; an additional 255 site cleanups were underway at the end of the state fiscal year. In addition, 434 "No Further Action" determinations were issued based on the results of site investigations or remedial actions performed satisfactorily prior to a property transfer.

 

ISRA Case Activities

TypeSFY96SFY97SFY98

Cleanups Underway236247255
Cleanups Completed2733 59
NFA Determinations403479434

 
Photo Description: Through a cooperative endeavor with NJDEP, Merck & Co., Inc. uses innovative technology to remove organic contamination from soil in a cleaning unit, pictured, owned by the company. The soil is cleaned through a low temperature thermal desorption method to meet NJDEP's Soil Cleanup Criteria and then is managed for beneficial reuse at Merck's Rahway facility.
Photo: Incinerator

Underground Storage Tanks

Significant progress continued in the remediation of underground storage tanks in SFY98, with 947 cleanups or closures completed. Of the 947 tank actions, 522 involved discharges with soil and/or ground water investigations. The remaining 425 removals were tanks without discharges. Data from 1996 to 1998 reveals that more than 2,400 leaking underground tanks were removed during that time period.

 

Underground Storage Tank Activities

TypeSFY96SFY97SFY98

Removals with Discharge710589522
Removals without Discharge499390425
Total1,209979947

 

Emergency Response and Environmental Action

The Site Remediation Program responded to 912 emergencies during SFY98, an average of 2.5 emergencies per day.

The Department "Hot Line" for reporting environmental concerns or discharge notifications answered 76,323 calls in SFY98, an average of 209 calls per day.

 

Environmental Response and Environmental Action

TypeSFY96SFY97SFY98

Emergency Response1,117982912
"Hotline" Calls Received77,81475,07576,323

 

Memorandums of Agreement and Administrative Consent Orders

When the Division of Responsible Party Site Remediation knows the individual or parties responsible for contamination at a site, a cleanup agreement is discussed. Once an agreement has been reached, an oversight document is issued and signed by both parties. Document types vary depending on the circumstances.

An Administrative Consent Order (ACO) is the standard control document issued for priority sites. A priority site is one where the Department will use public funds to conduct remedial activities unless a private party agrees to perform the cleanup. If public funds are used, known responsible parties unwilling to do the cleanup themselves will be directed to reimburse the state and may be required to pay three times the cost of the cleanup.

A Remediation Agreement is a contract between an ISRA responsible party and the Department. A Remediation Agreement allows the ISRA triggering event, such as a sale, transfer and/or closing of an industrial establishment, to proceed prior to the actual cleanup.

A Memorandum of Agreement (MOA) is executed when a responsible party, a land developer, or other cooperative party agrees to investigate and/or clean up a non-priority site or any portion thereof in accordance with the voluntary cleanup program.

There were 10 ACOs signed by responsible parties in SFY98 at priority sites with a total of $6.2 million in estimated remedial costs. Also, 116 Remediation Agreements were executed by private parties during SFY98 with a total of $51.8 million in estimated remedial costs. The number of MOAs signed by private parties and local governments during SFY98 was 2,048, an 11 percent increase from SFY97 and a 43 percent increase from SFY96.

It is important to note that there is not a one-to-one relationship between documents and sites or cleanups. One ACO could cover one or many sites and, conversely, an MOA could cover one site or a part of an overall site, such as only cleaning up leaking underground storage tanks at the location.

 

Oversight Documents Executed

TypeSFY96SFY97SFY98

Memorandums of Agreement

1,436

1,8422,048
Administrative Consent Orders9 7 10
Remediation Agreements6675116

 

Environmental Claims

The Environmental Claims Administration (ECA) processes claims under the New Jersey Spill Compensation Fund (Spill Fund). The Spill Fund provides compensation to individuals and businesses that have suffered direct or indirect damage resulting from a discharge of hazardous materials such as petroleum products.

In SFY98, ECA paid an estimated $1.5 million to compensate 182 claims for damages caused by discharges of hazardous substances. There were 35 administrative closures and eight claims denied. From SFY96 to SFY98, ECA paid more than $8 million dollars in compensation.

 

Spill Fund Claims

TypeSFY96SFY97SFY98

Claims Payments

215243182
Denials/Administrative Closures

87

4243

 

Photo

Photo Description: The Fort James Corporation's former Riegel Products site in Riegelsville, Warren County, undergoes cleanup of soil and building material, primarily contaminated with PCBs, as part of an Industrial Site Recovery Act case. Paper was manu-factured at this site for about 100 years prior to the early 1980s when opera-tions ceased.

 

Photo Description: A soil vapor extraction system is pictured operating at an Amerada Hess service station in Mountain Lakes, Morris County. The company installed the system in 1997 after a release of approximately 3,650 gallons of gasoline from an underground storage tank. Hess' exemplary response actions resulted in a recovery of more than 3,210 gallons of gasoline. The installation and operation of a permanent soil vapor extraction system occurred in less than three months following the release. Prompt response to this unfortunate event has prevented ground water contamination from leaving the boundaries of the site, while remaining contamination is controlled and cleaned up.

Photo

[ End of Report ]

 
PreviousTable of ContentsNext