Item |
Date |
Caption |
Image |
54. |
8
April 1922 |
"Sta.
4 26 - upstream side showing detail of trench bracing."
|
|
55. |
10
April 1922 |
"Detail
of faulty rock in bottom of trench. Sta. 5 67 - 5 77 - downstream
side Elev. 134."
|
|
56. |
10
April 1922 |
"Detail
of faulty rock in bottom of trench Sta. 6 07 downstream side Elev.
146 bottom of sheeting."
|
|
57. |
10
April 1922 |
"Showing
contact of sheet steel piling on rock at
Sta. 6 07 - Elev. 141.0 upstream side."
|
|
58. |
20
February 1922 |
"Looking
northwest showing portion of corewall between Stas. 2 00 and 4 50."
|
|
59. |
26
February 1922 |
"Looking
toward Sta. 0 00 along center line of corewall from railroad trestle
showing steel support for dredge pump."
|
|
60. |
15
March 1922 |
"Showing
a portion of corewall completed under Contract 2A to Elev. 240.0,
lower portion to Elev. 230.0."
|
|
61. |
10
April 1922 |
"Looking
toward Sta. 15 00 along center line of corewall from railroad trestle."
|
|
62. |
28
April 1922 |
"Jersey
City pipe line exposed new line on right, at a point between Peckmans
Brook crossing and Greenwood Lake branch of Erie Railroad."
|
|
63. |
12
May 1922 |
"North
Jersey District Water Supply Commission's field hospital, Wanaque
Dam."
|
|
64. |
12
May 1922 |
"Office
of Contractor's storehouse."
|
|
65. |
12
May 1922 |
"Field
Office of Assistant Engineer in charge of construction."
|
|
66. |
12
May 1922 |
"Mess
Hall and cooks - operated by Contractor, open to all employees of
Contractor and Commission."
|
|
67. |
12
May 1922 |
"Corner
of machine shop."
|
|
68. |
12
May 1922 |
|
|
69. |
12
May 1922 |
"Accounting
Department - Field Office."
|
|
70. |
30
June 1922 |
"Corewall
trench looking down from end of trench
Sta. 10 70. Showing concrete blanket in place and ready for grouting."
|
|
71. |
30
June 1922 |
"Looking
south from upstream side of corewall from
Sta. 2 50. Showing piling cut off at ground surface and clay puddle
placed between corewall and piling."
|
|
72. |
30
June 1922 |
"Looking
south from railroad trestle along upstream face of corewall. Removing
forms in foreground."
|
|
73. |
30
June 1922 |
"Concrete
mixing pland for Contract 2A composed of two 1 yd. Ransome steam
driven mixers."
|
|
74. |
30
June 1922 |
"Dredge
pump set up near Wanaque River upstream from dam to furnish water
for back fill operations."
|
|
75. |
21
July 1922 |
"Showing
a typical section of concrete forms for corewall. Sta. 7 00 Elev.
220-225."
|
|
76. |
21
July 1922 |
"Placing
concrete in corewall Sta. 7 05-7 55. Elev. 220-225."
|
|
77. |
21
July 1922 |
"Looking
north along top of corewall. Showing top of corewall completed to
Elev. 230.0."
|
|
78. |
21
August 1922 |
"Looking
south showing corewall practically completed to Sta. 10 71 and back
fill operations under way at north end."
|
|
79. |
3
October 1922 |
"Looking
north showing downstream embankment being sluiced into place after
having been dumped 6 yd. cars."
|
|
80. |
3
October 1922 |
"Showing
charging platform of dredge pump."
|
|
81. |
3
October 1922 |
"Looking
north along center line of corewall from Sta.
13 50."
|
|
82. |
3
October 1922 |
"Coffer
dam completed to allow corewall to be carried part way across Wanaque
River."
|
|
83. |
3
October 1922 |
"Looking
south from north end of Wanaque Dam. Showing moving form being set
up to raise corewall to Elev. 240 0."
|
|
84. |
3
October 1922 |
"Taken
from top of crusher looking north showing sand and gravel cut."
|
|
85. |
10
November 1922 |
"Panorama
of Wanaque Reservoir-View from south end of dam."
|
|
86. |
10
November 1922 |
"Wanaque
Dam-end of corewall under Contract 2A, movable concrete forms."
|
|
87. |
10
November 1922 |
"Wanaque
Reservoir looking south from E. R. Hewitt's house."
|
|
88. |
10
November 1922 |
"Wanaque
Dam-View from hill at south end showing placing of upstream embankment
by rolling and downstream by railroad haul and slushing it into
place."
|
|
89. |
8
November 1922 |
"Looking
south along center line of Great Notch Tunnel from a point north
of North Portal."
|
|