I-295 Bridge over Essex Avenue
July 2013
This view is looking north on I-295 over Essex Avenue.
November 2013
This view is looking
north on I-295 over Essex Avenue
with new temporary ramps in place.
January 2014
This view is looking north on I-295 over Essex Avenue
with the center bridge portion under construction.
May 2014
This view is looking north on I-295 over Essex Avenue.
October 2014
This view is looking north on I-295 over Essex Avenue
with traffic on the new bridge section in the center.
February 2015
This view is looking north on I-295 over Essex Avenue. The
new
retaining walls for the new roadway is being constructed.
May 2015
This view is looking north on I-295 at Essex Avenue.
The retaining walls are completed and
the
east bridge portion is under construction.
August 2015
This view is looking west on I-295 at Essex Avenue. The
east bridge portion is open to northbound I-295 traffic.
The remaining westerly portion of the bridge
(for I-295 southbound) is being constructed (background).
November 2015
This view is looking west on I-295 at Essex Avenue. The final
traffic pattern is in place for Contract 1. The remaining
westerly portion of the bridge (for future I-295
southbound roadway) is being constructed (background).
The
structural steel is in place and awaiting the concrete deck pour.
|